Meticulous attention to detail is hallmark of The Mai-Kai restoration project (May-June 2023 update)

Meticulous attention to detail is hallmark of The Mai-Kai restoration project (May-June 2023 update)

When The Mai-Kai reopens for guests, there will be tons of fresh features on the exterior: A lushly landscaped entryway with flowing water and rock work, a redesigned and immersive parking lot, plus a new outdoor bar and stage. But when you enter the main building, it will be like stepping into a time machine set for 1973.
RELATED: The Mai-Kai renovations, May-June 2023: Historic restaurant’s new infrastructure begins to take shape
SEE BELOW: May-June chronology | Design projects in depth

Scott "Flounder" Scheidly (left) and creative director "Typhoon Tommy" Allsmiller have mastered the art of restoring vintage lamps at The Mai-Kai. (Photos by Kern Mattei and Hurricane Hayward / June 2023)
Scott “Flounder” Scheidly (left) and creative director “Typhoon Tommy” Allsmiller have mastered the art of restoring vintage lamps at The Mai-Kai. (Photos by Kern Mattei and Hurricane Hayward / June 2023)

Making this feat a reality is a team of artists and craftspeople under the direction of manager Kern Mattei and creative director “Typhoon Tommy” Allsmiller. This over-arching job is mammoth, encompassing the restoration of the Molokai bar, eight elaborately themed dining areas, plus other guest spaces.

On top of this, Mattei is managing on-site workflow during the massive infrastructure project [see sidebar] while Allsmiller has his hand in any project that requires thematic design and an artist’s touch. In our last detailed story, we took a long look behind the scenes as Allsmiller and Scott “Flounder” Scheidly were deeply immersed in detail work throughout the sprawling 26,000-square-foot building.
PREVIOUS: Bora Bora building comes down as restoration efforts pick up steam
UPDATES: Latest news, photos of The Mai-Kai refurbishment

**************************************************

The Mai-Kai at Tiki Oasis
The Mai-Kai and The Atomic Grog are headed to Tiki Oasis
Join us for two special seminars at the world’s original Tiki weekender Aug. 2-6 in San Diego

**************************************************

In this update, we’ll catch up with the Orlando-area artists as they continue their mission to return The Mai-Kai to the same condition it was when the last major redesign was completed in the early 1970s. That’s when the last dining rooms were added and the building’s current footprint was solidified, some 15 years after its 1956 opening.

First, let’s walk through a chronological recap from May and June:

**************************************************

MAY AND JUNE UPDATES

Restored lamps in the Hawaii dining room, early May 2023. (Photo by Kern Mattei)
Restored lamps in the Hawaii dining room, early May 2023. (Photo by Kern Mattei)

EARLY MAY: Allsmiller and Scheidly were busy refurbishing lamps in the Hawaii dining area, the 60-capacity room to the right of the showroom stage. “They touched almost all of them,” Mattei said. They also finished the ceiling in Hawaii, adding new panels.

They were assisted by longtime Mai-Kai handyman Gustavo in removing the window between Hawaii and Samoa, then adding new wood and lighting. The window was cleaned and put back in place, restoring this little-known feature to its vintage condition:

Handyman Gustavo (from left),
(Photos by Kern Mattei)

They also started on the adjacent Moorea dining area, a 40-capacity room that’s slightly elevated to offer the most distant views of the Polynesian Islander Revue to the north beyond Hawaii. The opposite southern glass wall, featuring rare yellow Chinese jade tiles, offers views of the outdoor garden. The crew immediately targeted the woodwork, matting and lamps for repair.

The lamp-builders also pivoted back to the Tonga Room, the elevated 80-capacity space in the back of the showroom. They had made great progress there in previous months, but the huge space still had many lamps that needed work.

Below at left is a restored tapa in The Mai-Kai’s Hawaii Room. A vintage turtle shell lamp will be returned to the center (note the electrical outlet). At right are some of the many restored lamps in the Tonga Room.

Restored tapas in The Mai-Kai's Hawaii Room (left) and lamps in the Tonga Room. (Photos by Hurricane Hayward / May 2023)
(Photos by Hurricane Hayward / May 2023)

MID-MAY: Work wrapped up in the Hawaii dining room as Allsmiller and Scheidly put finishing touches on the lamps, walls and ceiling. “Once the turtle shells go back on the walls, it’s going to be beautiful in here,” Allsmiller said.

In their workspace in the main showroom, the lamp brigade finished all of the low-hanging lamps in the Tonga dining area, many created 50 years ago by the venerable Oceanic Arts. Those high in the A-frame will be touched later. Traditionally one of the darkest parts of restaurant, this area looks much brighter with all the lamps refurbished and featuring modern LED lighting.

In the left photo below, Allsmiller shows off a lamp project on May 18. At right, he points out work being done to restore an old framed tapa in the hallway near the Tonga Room and entrance to the kitchen. After the colors are touched up and it’s covered in Mod Podge, you won’t even notice, he said. “We’re trying to save them, bring them back.”

"Typhoon Tommy" Allsmiller shows off a lamp project (left) and points out work being done to restore an old framed tapa. (Photos by Hurricane Hayward / May 2023)
(Photos by Hurricane Hayward / May 2023)

Back in Moorea, Allsmiller explained how they’re trying to restore the walls even though some of the materials are no longer available. He said they’re using materials salvaged from elsewhere, then changing the design slightly so chair backs will no longer damage the matting. “We’re saving material and reusing it,” he said.

He said the typical plan of attack for each room is to work on the walls first and save the lamps for last, or whenever they’re waiting for materials. On May 18, I found them in the nerve center – the main showroom workspace – buried in new lamp projects.

Both Scheidly and Allsmiller were working on total rebuilds of old lamps from the Tonga Room, found broken and in bad shape (see photo below). “I like the challenge,” Allsmiller said of not having the blueprints. He said he can make an educated guess of what the lamps should look like. Schematics for some of the Oceanic Arts lamps were found in The Mai-Kai warehouse, but many others are mysteries.

Scott "Flounder" Scheidly (left) and "Typhoon Tommy" Allsmiller works on rebuilding vintage lamps at The Mai-Kai. (Photo by Hurricane Hayward / May 2023)
(Photo by Hurricane Hayward / May 2023)

Work was also progressing into Samoa, a secluded dining area that seats 44 in one of the oldest rooms at The Mai-Kai. The “demolition crew” had been busy tearing out all the old, damaged wall materials. This is a big help to the designers, allowing them to concentrate on restoration. Work was also advancing on the refurbishing of the ceiling and beams.

Continue reading “Meticulous attention to detail is hallmark of The Mai-Kai restoration project (May-June 2023 update)”

Minimalist Tiki

The Mai-Kai renovations, April 2023: Bora Bora building comes down as restoration efforts pick up steam

The Mai-Kai renovations, April 2023: Bora Bora building comes down as restoration efforts ramp up

The structural footprint of The Mai-Kai changed dramatically last month with the demolition of the long-dormant Bora Bora building, which will pave the way for a reimagined entryway and fully immersive tropical-themed parking lot, outdoor seating area and porte-cochère at the historic South Florida restaurant.

Previous coverage
* Behind the scenes at The-Mai-Kai as restoration ramps up in 2023
* The Mai-Kai officially begins work on first phase of $8.5 million renovation projects

The Mai-Kai's Bora Bora building on April 14 (left), two weeks before its removal. By April 29, all that remained was an empty lot on the northeast corner of the property that will be transformed into a new entry experience. (Photos by Hurricane Hayward and Kern Mattei)
The Mai-Kai’s Bora Bora building on April 14 (left), two weeks before its removal. By April 29, all that remained was an empty lot on the northeast corner of the property that will be transformed into a new entry experience. (Photos by Hurricane Hayward and Kern Mattei)

Amid the ruckus outside, the restoration efforts inside the main building advanced quietly but deliberately. Creative director “Typhoon Tommy” Allsmiller and fellow Orlando-area artist Scott “Flounder” Scheidly completed the New Guinea dining room, a vintage space that dates back to The Mai-Kai’s 1956 opening. They also restored the ceiling and walls near the Tonga dining room, and by the end of the month were full immersed in the Hawaii room.

Laser-focused on The Mai-Kai’s hundreds of custom lamps, they cranked out replicas and refurbished many originals created 50 years ago. After they finish, it will be impossible to tell which lamps are rebuilt and which are vintage, an over-arching theme of the restoration efforts.

"Typhoon Tommy" Allsmiller shows off a refurbished lamp at The Mai-Kai on April 25. He and fellow artist Scott "Flounder" Scheidly completed restoring all the lamps in the New Guinea dining room (right). (Photos by Hurricane Hayward)
“Typhoon Tommy” Allsmiller shows off a refurbished lamp at The Mai-Kai on April 25. He and fellow artist Scott “Flounder” Scheidly completed restoring all the lamps in the New Guinea dining room (right). (Photos by Hurricane Hayward)

Meanwhile, the back-of-house area was a total construction zone as crews prepared for the installation of a new bar and kitchen. Up on the roof, workers were busy sealing the main A-frame and working on new vents, along with the structures to hold the new air-conditioning system.

After electrical work was done, a painting crew put the finishing touches on the men’s restroom. Electricians continued an infrastructure overhaul, preparing for the upcoming installation of a new circuit breaker system.

Despite all the chaos, manager Kern Mattei managed to crank out another round of The Mai-Kai’s signature cocktail quarts and gallons to go on April 26-27. Depending on the progress on the electrical work., which may force the shutdown of the bar’s coolers, the next chance to enjoy the classic tropical drinks may take place only at The Hukilau weekender in June.

Photos provided by manager Kern Mattei show the progress of work on The Mai-Kai's soaring main A-frame. The roof was sealed to prevent leaks (left), then repainted.
Photos provided by manager Kern Mattei show the progress of work on The Mai-Kai’s soaring main A-frame. The roof was sealed to prevent leaks (left), then repainted.

Below are updates on all the work that took place in April, including video and many exclusive photos.

Jump to April news and updates below
* Bora Bora Room removed | Photo gallery
* Dining rooms return to vintage glory | Photo gallery
* Work begins on new bar and kitchen
* Former Molokai bar waitress remembered

UPDATES: Get the latest news and photos on our social media pages
* Facebook | Instagram | Twitter
Atomic Grog blog: Recent social media posts, past coverage

A view of The Mai-Kai from Federal Highway on April 7 after the thatching of the A-frame roofs over the rear dining rooms was completed. (Photo by Hurricane Hayward)
A view of The Mai-Kai from Federal Highway on April 7 after the thatching of the A-frame roofs over the rear dining rooms was completed. (Photo by Hurricane Hayward)

It’s no surprise that April saw an acceleration of renovation work on multiple fronts. In March, The Mai-Kai officially began the $8.5 million project after three permits cleared the way for three major projects:
* Repair and restoration of the porte-cochère and thatched roofing.
* Removal of the Bora Bora building.
* Interior renovation, including a new bar and kitchen.

The repairs and refurbishments became necessary after the 26,000-square-foot restaurant suffered a catastrophic roof collapse over the kitchen in late October of 2020. The plans – which include both restoring the main building and upgrading and enhancing the parking lot and back of house – became clear after the founding Thornton family sold a majority interest to a new ownership team led by the Barlington Group and historic preservationist Bill Fuller.

The permit approvals restarted the roof thatching project in March. By April, thatching was completed on the porte-cochère as well as the A-frame roofs over the back dining rooms. All that remained was detailing and finishing work, which will happen later.

Outside under the porte-cochère on April 14, a crew works on spackling and smoothing the wood, getting it ready to be finished. (Photo by Hurricane Hayward)
Outside under the porte-cochère on April 14, a crew works on spackling and smoothing the wood, getting it ready to be finished. (Photo by Hurricane Hayward)

As April progressed, The Mai-Kai applied for three new permits that will keep projects moving quickly. On April 25, the city of Oakland Park issued a mechanical permit that will allow for the installation of the new kitchen. It won’t expire until Oct. 23, which fits in with the timeline we’re hearing about a reopening coming in the fall.

A mechanical permit for “fire suppression” was applied for in April, then issued in May This likely covers not only a new sprinkler system, but a fine-tuning off The Mai-Kai’s elaborate rooftop exhaust system that pulls smoke from the main showroom after the fire-dancers perform in the Polynesian Islander Revue. Established in the early 1960s, it’s the oldest continually-running authentic South Seas stage show in the United States (including Hawaii).

Continue reading “The Mai-Kai renovations, April 2023: Bora Bora building comes down as restoration efforts pick up steam”